Considering the current value of FCT, Stamp-IT has retired one of its physical servers and one authority node in order to reduce costs. Accordingly, we will reduce our efficiency to 0% so that we continue to receive the same amount of FCT.

We continue to operate our physical infrastructure, with 16 cores in one datacenter. We currently host two instances of factomd running on the mainnet (one authority + one backup) and another one running on the testnet. We will add a second testnet node shortly to compensate for the recent retirement of a testnet node.
 